The Wastewater Utility implements an annual sanitary sewer rehabilitation and/or replacement project as part of its ongoing capital improvement program. The replacement project consists of various sewer main, manhole, and side sewer replacements. The sewer infrastructure to be replaced was chosen based on the severity of existing issues found through field observations and inspections. The project is located within city right-of-way and on private property within city easements.

This project will fix or replace defective sanitary sewer facilities in seven different sites in the north half of Renton and is divided into two phases. Phase 1 is comprised of right-of-way work for Sites 1, 2, 3 and 6. Phase 2 is comprised of private and right-of-way work for Sites 4, 5 and 7.

Contract Award Information - Construction Phase 1

Phase 1 of the Sanitary Sewer Replacement project went out to bid on July 11, 2024. Rodarte Construction, Inc., was the apparent low bidder, with a bid of $780,857.52. Council awarded the project to Rodarte Construction at its regular meeting on August 5, 2024.

Project Scope

Phase 1

 The scope for this portion of the project includes the following work in the ROW:

  •  Furnish and install approximately 740 - linear feet of 8-inch sewer main, including 8-inch cleanout(s).
  •  Furnish and install approximately 10 - linear feet of 12-inch sewer main.
  • Furnish and install one Type 1 48-in Diameter manhole.
  • Trench excavation, including removal and abandonment of existing utilities, disposal of excavated material, shoring, removal of existing unsuitable material, and dewatering.
  • Removal and replacement of asphalt concrete pavement, asphalt overlay, concrete curbs, gutters, and sidewalks.
  • Installing and maintaining adequate TESC measures and restoring all disturbed areas.
  • Temporary traffic control measures following the contract documents and applicable City of Renton and MUTCD standards.
  • CCTV inspection of sewer mains.
  • Bypass pumping.

Phase 2

  • Furnish and install approximately 740 - linear feet of 8-inch sewer main, including 8-inch cleanout(s).
  • Furnish and install approximately 10 - linear feet of 12-inch sewer main.
  • Furnish and install one Type 1 48-in Diameter manhole.
  • Trench excavation, including removal and abandonment of existing utilities, disposal of excavated material, shoring, removal of existing unsuitable material, and dewatering.
  • Removal and replacement of asphalt concrete pavement, asphalt overlay, concrete curbs, gutters, and sidewalks.
  • Installing and maintaining adequate TESC measures and restoring all disturbed areas.
  • Temporary traffic control measures following the contract documents and applicable City of Renton and MUTCD standards.
  • CCTV inspection of sewer mains.
  • Bypass pumping.


Project Update

Project Update 9/18/2024

Phase 1

Phase 1 of the Sanitary Sewer Replacement project went out to bid on July 11, 2024. Rodarte Construction, Inc., was the apparent low bidder, with a bid of $780,857.52. Council awarded the project to Rodarte Construction in their August 5, 2024, meeting. Construction is anticipated to start in September.

Phase 2

The Sanitary Sewer Replacement Phase 2 Project has finished 60% design review, and our consultant is working towards 90% design. Due to delays in design, permitting, and obtaining temporary construction easements, the project is expected to advertise for bid at the beginning of next year. Construction is expected to begin spring 2025.

Site Descriptions

Site 1: Adjacent to 1521 Kirkland Avenue NE
Installation of new internal drop connection in MH5990 for the incoming sewer from the north.

Site 2: NE 4th Street near the eastern driveway of the Cedar Park Apartments. Installation of a new manhole at the intersection of two existing sewers to allow the abandonment of the failing downstream sewer main on NE 4th Street.

Site 3: 3500 block of NE 7th Place. Replacement of the failing sewer main and side sewer stubs between the existing sewer manhole near 3500 NE 7th Place and the manhole near the intersection of NE 7th Place and NE 6th Place.

Site 4: 3900 and 4000 blocks of NE 6th Street and the 600 block of Tacoma Avenue NE. Installation of new sewer main lines in NE 6th Street and replacement of the existing sewer main in Tacoma Avenue NE. Work also includes connection of the existing homes, which are currently connected to the existing sewers, into the new sewer mains. Abandonment of the existing sewer mains that are in easements in the adjacent properties’ backyards.

Site 5: 3300 and 3400 blocks of NE 6th Street. Installation of new sewer main lines in NE 6th Street. Work also includes connection of the homes on the north side of NE 6th Street into the new sewer main lines. Abandonment of the failing sewer main lines located in the easement along the north property lines of the affected properties.

Site 6: Intersection of NW 7th Street and Taylor Avenue NW Elimination of backwater problems in MH0579. Construction method to-be-determined.

Site 7: 700, 800, 900 and 1000 blocks of Monroe Avenue NE. Replacement or Rehabilitation of the existing sewer main located along the west property lines of those homes on the west side of Monroe Avenue NE.

Vicinity Maps

Site 1: Adjacent to 1521 Kirkland Avenue NE

Site 2: NE 4th Street near the eastern driveway of the Cedar Park Apartments

Site 3: 3500 block of NE 7th Place

Site 4: 3900 and 4000 blocks of NE 6th Street and the 600 block of Tacoma Avenue NE

Site 5: 3300 and 3400 blocks of NE 6th Street

Site 6: Intersection of NW 7th Street and Taylor Avenue NW

Site 7: 700, 800, 900 and 1000 blocks of Monroe Avenue NE

Site 1 Construction Notice – Mailed September 4, 2024

Sanitary Sewer Replacement Project Site 1, Phase 1 (Near the Southwest corner of NE 16th St & Kirkland Ave NE)

This is a construction notification for the Sanitary Sewer Replacement Project, Phase 1, a crucial sewer infrastructure upgrade project. Construction is tentatively scheduled to begin in mid-September 2024. Further information will be communicated as construction progresses.

The project aims to replace old or failing sanitary sewer infrastructure located south of the southwest corner of the NE 16th St and Kirkland Ave NE intersection, within the right-of-way in proximity to your property. (View map on reserve side.) The project involves the replacement of a segment of the 12-inch sewer main and a portion of the adjacent curb, gutter, and sidewalk. We will try to minimize disruption to your daily routine. However, please know that sidewalk use, bus stop access, and parking may be temporarily restricted based on the contractor’s daily construction activities. 

Site 2 Construction Notice – Mailed September 4, 2024

Sanitary Sewer Replacement Project
Site 2, Phase 1 (NE 4th Street near the
southeast driveway entrance of the Cedar Park Apartments)

This is a construction notification for the Sanitary Sewer Replacement Project, Phase 1, a crucial sewer infrastructure upgrade project. Construction is tentatively scheduled to begin in mid-September 2024. Further information will be communicated as construction progresses.

The project aims to replace old or failing sanitary sewer infrastructure near the NE 4th Street Cedar Parks Apartment driveway entrance. (View map on reserve side.) It involves replacing an existing sewer cleanout with a manhole and asphalt restoration. We will try to minimize disruption to the complex and daily routine. However, please know that access from the NE 4th Street driveway will be temporarily restricted based on the contractor’s daily construction activities.

Site 3 Construction Notice – Mailed September 4, 2024

Sanitary Sewer Replacement Project Site 3, Phase 1 (3500 block of NE 7th Place)

This is a construction notification for the Sanitary Sewer Replacement Project, Phase 1, a crucial sewer infrastructure upgrade project. Construction is tentatively scheduled to commence in mid-September 2024. Further information will be communicated as we get closer to construction.

The project aims to replace old or failing sanitary sewer infrastructure in the right-of-way on NE 7th Pl. (View map on reserve side.) The project includes a new 8-inch sewer main and an asphalt road overlay.

We will do our best to limit the disruption to your daily schedule; parking and vehicular access to your home may be temporarily restricted depending on the contractor’s schedule, so please plan accordingly.

Site 6 Construction Notice – Mailed September 4, 2024

Sanitary Sewer Replacement Project Site 6, Phase 1 (NW 7th St [S 122nd St] & Taylor Ave NW)

This is a construction notification for the Sanitary Sewer Replacement Project, Phase 1, a crucial sewer infrastructure upgrade project. Construction is tentatively scheduled to commence in mid-September 2024. Further information will be communicated as we get closer to construction.

The project aims to replace old or failing sanitary sewer infrastructure in the right-of-way adjacent to your property, located in NW 7th Street (S 122nd Street) and Taylor Avenue NW. (View map on reserve side.) The project includes a new 8-inch sewer main and an asphalt road overlay.

We will do our best to limit the disruption to your daily schedule; parking and vehicular access to your home may be temporarily restricted depending on contractors schedule, so please plan accordingly.