Open House presentation on February 22, 2024
Burnett Ave S and Williams Ave S Water Quality Retrofit Project
TOPICS TO DISCUSS
Brief Background
Location
Costs
Construction Timeline
Community Considerations
What to Expect
Project Team & Contact Information
Questions
A BRIEF BACKGROUND
Project Origin
Downtown Utilities Improvement Project
Project Scope
Installation of water quality treatment facilities and replacement of undersized and aging stormwater and wastewater infrastructure
Acknowledgement
Project is partially funded by the Washington State Department of Ecology Stormwater Grant Program and the King County Flood Control District Subregional Opportunity Fund
PROJECT AREA
Vicinity Map
IMPACTED STREETS
Burnett Ave S
Williams Ave S
S Tobin St
S Riverside Dr
RESTORATION
WATER
Relocation of existing Water Services to enable installation of new storm system
CORE WORK
WASTEWATER
Approximately 450 feet of new sanitary sewer pipe & laterals
SURFACE WATER
Approximately 2,650 feet of new stormwater pipes and two water quality treatment facilities
RESTORATION
CURB & GUTTER
The replacement of curbs, gutters, sidewalks and ramps where impacted by installation of new utilities
PROJECT COSTS AND GRANT FUNDING
BUDGET
Project Budget1: $ 4.37 M
Estimated Remaining Project Costs: $ 3.74 M
2024 Combined Surface Water and Wastewater Utility CIP Budgets, Includes Grant
Funding
PROJECT GRANT FUNDING
Washington State Department of Ecology Water Quality Combined Financial Assistance Agreements
2020 Grant Agreement for Design Phase: $277,500
2023 Grant Agreement for Construction Phase: $927,000
Total Department of Ecology Grant Funding: $1,204,500
King County Flood Control District Subregional Opportunity Fund
2024 Subregional Opportunity Fund Allocation: $194,950
Total Grant Funding for over lifetime of Project: $1,399,450
PROJECT TIMELINE
Ongoing public outreach efforts
Continuing Engagement with Residents & Businesses
On-Line Open House/Office Hours
Project Website
Scheduled Notifications
April 2024
Solicit Bids for Construction
By June 2024
Award Construction Contract
Utility Coordination
By July 2024
Pre-Construction Meeting
Contractor Submittals
Contractor Mobilization
Construction Survey
Utility Locates
Layout
July 2024 - Spring 2025
Construction of utility work followed by street restoration
Begin with storm system improvements on Williams Ave S near Cedar River (proposed)
Move south along Williams Ave S and Burnett Ave S towards S 2nd St
Expected 9-month construction window
COMMUNITY CONSIDERATIONS
GENERAL PUBLIC
Vehicular Traffic (Local Traffic, Through Traffic, Public Transportation)
Pedestrian Routes
Residential Access and Parking
BUSINESSES
Commercial Access and Parking
Business Hours
Deliveries
DOWNTOWN EVENTS AND ACTIVITIES
Farmers Market
Renton River Days
Cruise the Loop
WHAT TO EXPECT
TRENCHING
Begin construction at Williams Ave S near Cedar River (proposed)
Estimated 7am-4pm construction hours
No overnight work will be allowed
PARKING RESTRICTIONS AND PEDESTRIAN ROUTES
Minor parking restriction and pedestrian detours near work zones
TRAFFIC MANAGEMENT
Where possible, a minimum of 1-lane of traffic will be open to traffic at all times
During construction hours, detours will be established when traffic cannot safely proceed through the work zones
Additional Lanes may be open after construction hours when possible
PUBLIC OUTREACH
Public outreach will begin prior to start of construction and will continue throughout, including:
Advanced notice of construction impacts to residents and businesses (on-street parking restrictions, interruption to water service, other impacts).
Updates on construction progress
Signage will be provided to direct people to businesses located within and surrounding the work zones.
PROJECT TEAM
DESIGN CONSULTANT
BHC CONSULTANTS, INC
Seattle, WA
BECCA OCHILTREE, PE
Project Manager
CITY STAFF
PROJECT TEAM
TROY SOLLY, PE
Lead Project Manager
JOE FARAH, PE
Surface Water Utility Manager
Subject Matter Experts and Supporting PMs
Water Utility Engineering, Abdoul Gafour
Wastewater Utility Engineering, Mike Benoit
COMMENTS OR QUESTIONS?
PHONE
(425) 430-7313
EMAIL
[email protected]
WEBSITE
Rentonwa.gov/BURNETTWILLIAMS
in the pipeline, online soon!