Impact Traffic Report

Week of August 19-23, 2019

Projects are weather permitting and unless otherwise noted streets always remain open.

South 14th Street
Monday-Friday

Road Closure on South 14th Street between Smithers Avenue S through Davis Avenue S for utility construction. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Patrick DeCaro, 425-207-6013.

Renton Avenue South (Earlington Hill)
Monday-Friday, 7 a.m. to 5 p.m.

Intermittent lane closures at S 132nd Street for storm water utility work.  Approved traffic control plans have been issued for all work and will be followed. Questions about this work can be directed to Michelle Faltaous, 425-430-7301 or Todd Freih, 206-999-1832.

S 130th Street
Monday-Friday, 7 a.m. to 10 p.m.

S. 130th Street will be closed west of Renton Avenue for utility work.  Approved traffic control plans have been issued for all work and will be followed.  Any questions about this work can be directed to Michelle Faltaous, 425-430-7301 or Todd Freih, 206-999-1832.

Talbot Road South
Monday-Friday, 8:30 a.m. to 3:30 p.m.

Single lane closures on Talbot Road South in the vicinity of Valley Medical Hospital related to the construction of the new Medical Office Building.  Questions may be directed to Tom Main, 206-999-1833.

South 23rd Street
Now through August 23

Full street closure of South 23rd Street immediately east of Talbot Road South and east to Morris Ave South for a period of up to four (4) weeks, from July 23 to August 23, 2019, in order to allow the abatement of potential hazards and repair of the sinkhole from an abandoned coal mine located under the right-of-way. Access will remain open to homes on Morris Ave South. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Tom Main, 206-999-1833.

King County Eastside Sewer Interceptor Rehabilitation project

Logan Avenue N
Current through January 1, 2020

Potential intermittent lane closures along Logan Avenue N between N 6th Street and near Garden Avenue N in support of the King County Eastside Sewer Interceptor Rehabilitation project.  A traffic control plan is being reviewed by City Staff and will be approved prior to any lane closures. Questions may be directed to Brad Stocco, 425-282-2373 or Rohini Nair, 425-430-7298.

Burnett Avenue N
Current through January 1, 2020

Full Road Closure on Burnett Avenue N between N 6th Street and approximately 100 feet south of N 6th Street. Road closure is in support of the King County Eastside Sewer Interceptor Rehabilitation project. Both the City of Renton and King County’s Wastewater Division have reached out to property owners along the approved detour route and to affect parties providing advanced notification of the proposed road closure and detour route. In addition, notification was provided in the Renton Reporter and signage will be provided in the field prior to roadway closure. Resolution 4378 has been approved by City Council for the roadway closure of Burnett Avenue N.  An approved detour route have been issued for the roadway closure and will be followed.  Questions may be directed to Brad Stocco, 425-282-2373 or Rohini Nair, 425-430-7298.

Week of August 26-30, 2019

Projects are weather permitting and unless otherwise noted streets always remain open.

South 14th Street
Monday-Friday

Road Closure on South 14th Street between Smithers Avenue S through Davis Avenue S for utility construction. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Patrick DeCaro, 425-207-6013.

Renton Avenue South (Earlington Hill)
Monday-Friday, 7 a.m. to 5 p.m.

Intermittent lane closures at S 132nd Street for storm water utility work.  Approved traffic control plans have been issued for all work and will be followed. Questions about this work can be directed to Michelle Faltaous, 425-430-7301 or Todd Freih, 206-999-1832.

S 130th Street
Monday-Friday, 7 a.m. to 10 p.m.

S. 130th Street will be closed west of Renton Avenue for utility work.  Approved traffic control plans have been issued for all work and will be followed.  Any questions about this work can be directed to Michelle Faltaous, 425-430-7301 or Todd Freih, 206-999-1832.

Talbot Road South
Monday-Friday, 8:30 a.m. to 3:30 p.m.

Single lane closures on Talbot Road South in the vicinity of Valley Medical Hospital related to the construction of the new Medical Office Building.  Questions may be directed to Tom Main, 206-999-1833.

South Puget Drive
Monday-Friday, 8:30 a.m. to 3:30 p.m.

Westbound lane closure of South Puget Drive in the 1500 Block.  Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Tom Main, 206-999-1833.

King County Eastside Sewer Interceptor Rehabilitation project

Logan Avenue N
Current through January 1, 2020

Potential intermittent lane closures along Logan Avenue N between N 6th Street and near Garden Avenue N in support of the King County Eastside Sewer Interceptor Rehabilitation project.  A traffic control plan is being reviewed by City Staff and will be approved prior to any lane closures. Questions may be directed to Brad Stocco, 425-282-2373 or Rohini Nair, 425-430-7298.

Burnett Avenue N
Current through January 1, 2020

Full Road Closure on Burnett Avenue N between N 6th Street and approximately 100 feet south of N 6th Street. Road closure is in support of the King County Eastside Sewer Interceptor Rehabilitation project. Both the City of Renton and King County’s Wastewater Division have reached out to property owners along the approved detour route and to affect parties providing advanced notification of the proposed road closure and detour route. In addition, notification was provided in the Renton Reporter and signage will be provided in the field prior to roadway closure. Resolution 4378 has been approved by City Council for the roadway closure of Burnett Avenue N.  An approved detour route have been issued for the roadway closure and will be followed.  Questions may be directed to Brad Stocco, 425-282-2373 or Rohini Nair, 425-430-7298.

 

City of Renton | All Rights Reserved | Powered by CivicLive | © 2019 West Corporation. | Disclaimer