Project Description
Bridge preservation, seismic retrofit and painting of the Bronson Way Bridge, a three span bridge over the Cedar River, located in downtown Renton. The main span (span 2) consists of two steel plate girders connected by steel deck beams supporting the bridge deck.
Contractor: Combined Construction, Inc.
Construction Estimate: $2.5 million (rounded)
This Project in This Week in Renton (TWIR)
-
TWIR - July 12, 2023
-
TWIR - May 12, 2023
-
TWIR - May 5, 2023
-
TWIR - Sept. 22, 2022
Completed Construction
Work Element (1) - Bridge Painting
Steel main span:
-
Installation (and removal) of temporary work access and containment system
-
Removal of existing paint system
-
Sealing and/or repair of areas with pack rust
-
Application of new protective paint system (zinc primer, intermediate, color finish)
Work Elements (2) - Seismic Retrofit & (3) Deck Maintenance
Seismic retrofit activities for steel main span included:
-
Temporarily elevate using hydraulic jacks
-
Remove existing rocker and fixed bearings
-
Install new elastomeric bearing pads on new concrete bearing pedestals
Maintenance activities for bridge deck included:
-
Remove existing asphalt overlay wearing course
-
Repair underlying concrete deck (as needed)
-
Remove existing steel slide plate expansion joints
-
Repair existing concrete curbs
-
Adjust bridge drain inlet grates
-
Install new compression seal expansion joints
-
Install new waterproofing membrane on concrete deck
-
Install new asphalt overlay wearing course on concrete deck
Before and After Photos - Phase I