The Downtown Utility Project upgrades water, sewer and stormwater utilities to address current use and support future development needs within the downtown core. Upgrades are needed now because some underground pipes are past their useful life, in poor condition, lack capacity and/or require costly maintenance. This project precedes future work that will include streetscape improvements and the conversion of S 2nd St and S 3rd St to two-way operations.
Construction planned: spring 2021 - fall 2022
Water work on S 2nd between Whitworth Ave S and Rainier Ave S will continue through next week with some spot work in the area..S 2nd St north of the island will be closed. Access remains open on the lanes south of the island. The available lanes will depend on the work being done at that time.
Work continues on Rainier Ave S and S 3rd St to complete installation of a storm drain access lid. Concrete was poured Thursday February 3rd and will need to cure for the next two weeks.
Lanes will be restricted as needed, but through access of the intersection will be maintained. This work is anticipated to proceed through mid-February. After curing we will return to complete paving at the intersection.
Typical work hours: Weekdays, 7 a.m. to 5 p.m.
Construction impacts: Check out the project page for additional information and detailed construction impacts.