On September 14, 2015, a construction contract was awarded to Johansen Excavating, Inc. of Buckley, WA for $4,424,412.72.
Construction started November 9, 2015 and was substantially completed July 14, 2016, though some follow-up "punchlist" and landscape establishment work is still going on.
Traffic on Logan Avenue North has been restricted to one-way northbound for most of the duration but was re-opened to two-way traffic on July 7, 2016.