Downtown Utility Improvement Project

Contact Information
Utility Systems Division Engineering Team
Renton, WA 98057

DUIP Project Map

Click to download larger image

Construction News Changes Rapidly

Stay Up-to-Date using one or all of these methods

Safety First

For the safety of pedestrians and transit operators, vehicle access between S 2nd St and S 3rd St and Logan Ave S and Burnett Ave S is for transit vehicles only. Personal vehicle access is not permitted.

Overall Construction Update

Current construction efforts are putting our completion ahead of schedule, with storm utility improvements now complete.

Remaining sewer utility work has reached 90% completion and will be completed this fall with low-impact, cured in-place lining happening through spring 2022.

Parking

Parking Sign

We are trying to minimize parking impacts as much as possible.

The City Center Parking Garage offers free parking for access to downtown businesses through December of this year and can also be used by residents during construction. The garage is accessible between 5 a.m. and 11 p.m., Sunday through Thursday, and from 5 a.m. to 1 a.m. on Friday and Saturday. Overnight parking is allowed during our construction efforts, but please note that all garage doors are locked outside of these hours. In addition, street parking is available on S 3rd St.

Traffic Detour and Large Deliveries

During installation of the utilities, there will be times when it is not safe for traffic to proceed through the work zones. As a result, full or partial road closures with detours can be expected during different phase of the project. We will provide detailed updates of closures and detours as construction progresses.

While these detours are necessary for completion of the project, we do want to ensure that businesses are still able to operate and receive product deliveries essential to their operations. If you are currently impacted by road closures or detours and have an upcoming product delivery, please call 425-363-1007 for help with coordination of deliveries larger than a single unit.

S 2nd Street Detour Route

While work is occurring on S 2nd St between Morris Ave S and Shattuck Ave S, the two lanes north of the center island will remain open to traffic, while the two lanes south of the center island will be closed. Access to and from Morris Ave S and Shattuck Ave S will be set up through the intersections from north of the center island. Access to and from Whitworth Ave S will be maintained during work hours but limited to when flaggers are at the intersection. Follow posted signage and flaggers for access.

S 2nd Street Daytime Access

Due to the lack of a traffic signal at the intersection of Whitworth Ave S and S 2nd St, access to and from Whitworth Ave S at S 2nd St will be closed overnight. Drivers will need to access Whitworth Ave S from S 3rd St, as shown on the map.

S 2nd Street Nighttime Route

Once we’ve completed sewer utility work Whitworth Ave S to Shattuck Ave S, we will move the work area north of the island and move west towards Rainier Ave S. Please follow posted signage and flaggers during shifts in access.

Current Work Areas

Current Work Areas
1. Stormwater utility on Whitworth Ave S

Stormwater utility improvements on Whitworth Ave S between S 2nd and S 3rd streets continues.

This work is expected to be complete by the end of October.

2. Sewer on S 2nd St

Construction on the sewer main in S 2nd St will continue to move both east and west, ultimately all the way to Logan Ave S and Rainier Ave S. This work is anticipated to last through the month of November. Access to and from S 2nd St will be limited at Morris Ave S, Whitworth Ave S, and Shattuck Ave S. Please reference the S 2nd Street Detour Maps above for access.

Remaining Work Areas

DUIP Remaining Work Areas

1. S 2nd St Sewer (October - November 2021)

The ongoing sewer main installation has reached its last leg with the current work in S 2nd St. Work will continue from the low point at the intersection of Whitworth Ave S & S 2nd St, moving west to Rainier Ave S and east to Morris Ave S.

2. Water Utility (December 2021 - January 2022)

Water utility work will begin later this year through early next year in the following locations:

  • Whitworth Ave S and Shattuck Ave S, between S 2nd St and S 3rd St.
  • Water utility work on S 2nd St from Whitworth Ave S to Rainier Ave S.
  • Water utility work will occur south of  S 3rd St at Whitworth Ave S and Smithers Ave S.

3. Rainier Ave S Sewer Access Lid (December 2021)

We will return to the intersection of Rainier Ave S and S 3rd St to complete installation of a sewer access lid. Lanes will be restricted as needed, but through access of the intersection will be maintained.

Water Utility Wrap-up (not on map) 
Late Fall 2021 - Early Winter 2022

Not shown in the map are final steps to complete water utility improvements such as installing final services, connections and pressure testing. Water utility shutoffs are anticipated during service connections. We will reach out with prior notifications prior to shutoffs.

Paving and Restoration (not on map)
Spring - Fall 2022

Final Paving and restoration of downtown curbs, sidewalks and roads will begin in the spring following completion of utility work.

Cured In-place Lining (not on map)
November 2021 - December 2021

Low-impact cured in place work to repair and reinforce existing utility infrastructure will occur throughout the project area.

Work Hours

  • 7 a.m. - 6 p.m. construction hours

  • 5 a.m. – 12 p.m. Tuesday construction hours while work is in the vicinity of the farmer’s market.
  • Limited overnight work is expected

  • Equipment will stay in work zones overnight

What to Expect

Trenching

  • Multiple trenches will be open at a time for utility work

  • There may be multiple utilities on the same block that require separate trenching efforts

Parking Restrictions & Pedestrian Routes

  • Expect parking restrictions and pedestrian detours near work zones

  • We know there will be impacts, but we will do everything we can to maintain access

Traffic Management

  • Where possible, a minimum of 1-lane of traffic will be open to traffic at all times
  • During construction hours, detours will be established when traffic cannot safely proceed through the work zones

  • Additional lanes may be open after construction hours when possible and safe.

  • Detour and traffic signs will signal vehicle reroutes and access

Road Closures

  • Block by block sections of S. 3rd Street will be closed to vehicle access during the working day
  • Closure of each section is expected to last approximately 2-4 weeks
  • For safety reasons, roads will be closed in areas where deep trenching will occur

  • Closure of roads will be coordinated with the Wells – Williams Project, where applicable

Related Downtown Projects

The South Wells Avenue and South Williams Avenue Conversion Project is under a separate contract but will likely be conducted in the same timeframe. This project will improve intersections, add new signals, and convert both streets to two-way operations.

The adopted Civic Core Action Plan explores ways to pedestrian and bicyclists facilities and enhancements, traffic operation and circulation improvements to Downtown. The improvements include adding raised intersections with bulb outs, lighting, street furniture, streetscape, bike racks, signage, wayfinding and street conversions.

Project Files

Newsletters

October 2021

  • 10/22/2021 - Downtown Renton Construction: Wells Ave S and Williams Ave S open to one-way traffic
  • 10/15/2021 - Downtown Renton Construction: Plan to continue paving S 3rd St next week
  • 10/7/2021 - Downtown Renton Construction: S 3rd St to be closed during the day from Burnett Ave S to Main Ave S for paving
  • 10/1/2021 - Downtown Renton Construction: Preparing to pave S 3rd St

September 2021

  • 9/24/2021 - Downtown Renton Construction: Utility work continues in downtown Renton
  • 9/17/2021 - Downtown Renton Construction: Utility work continues in downtown Renton
  • 09/10/2021 - Downtown Renton Construction: Upgrades resuming on Houser Way S
  • 09/03/2021 - Downtown Renton Construction: Progressing intersection work in downtown Renton

August 2021

  • 08/27/2021 - Downtown Renton Construction: Progressing intersection work in downtown Renton
  • 08/20/2021 - Downtown Renton Construction: Progressing intersection work in downtown Renton
  • 08/16/2021 - Downtown Renton Construction: Intersection work in downtown Renton
  • 08/11/2021 - Downtown Renton Construction: Night work at intersection of S 3rd St and Rainier Ave S.
  • 08/06/2021 - Downtown Renton Construction: Plan ahead for detours with intersection work

July 2021

  • 7/30/2021  - Downtown Renton Construction: Reopening Shattuck Ave S & S 3rd St intersection tonight
  • 7/27/2021 - Downtown Renton Construction: Watch your step; avoid the sticky sealant!
  • 7/23/2021 - Downtown Renton Construction: Shattuck Ave S Intersection Work and S 3rd St Road Closure
  • 7/21/2021 - Renton Downtown Utility Improvement: Shattuck Ave S Intersection Work and S 3rd St Road Closure
  • 7/16/2021 - Downtown Renton Construction: Time for the clocktower to come home!
  • 7/9/2021 - Downtown Renton Construction: Sidewalks on S 3rd St have reached substantial completion
  • 7/6/2021 - Downtown Renton Construction: Temporary two-way cul-de-sac on Wells Ave S
  • 7/2/2021 - Downtown Renton Construction: Continuing to progress utility and sidewalk work

June 2021

  • 6/25/2021 - Downtown Renton Construction: Sunny days lead the way to the farmer’s market.
  • 6/18/2021 - Downtown Renton Construction: Follow the “Yellow Brick Road” for business access during construction
  • 6/17/2021 - Downtown Construction - Overnight Closure of S 3rd Street
  • 6/11/2021 - Downtown Renton Construction: Continuing utility and sidewalk work in downtown Renton
  • 6/3/2021 - Downtown Renton Construction: Storm Utility work on S 3rd St

May 2021

  •  5/21/2021 - Downtown Renton Construction: Renton Farmers Market is returning for its 20th season
  • 5/14/2021 - Downtown Renton Construction: The clocktower takes a ride to its new temporary home
  • 5/7/2021 - Downtown Renton Construction: Temporarily relocating the clocktower and continuing utility work in downtown Renton

April 2021

  •  4/30/2021 - Downtown Renton Construction: Renton Farmers Market is returning for its 20th season
  • 4/23/2021 - Downtown Construction: Update on downtown Renton intersection work
  • 4/16/2021 - Renton Downtown Utility Improvement Project Update

Mailings and Flyers

Webinar Recording

Miss our March 11, 2021, webinar? Here it is:

 

Along with presentation slides.

Your Title VI Civil Rights

The City of Renton hereby gives public notice that it is the City's policy to assure full compliance with Title VI of the Civil Rights Act of 1964, the Civil Rights Restoration Act of 1987, and related statutes and regulations in all programs and activities. Title VI requires that no person shall, on the grounds of race, color, sex, or national origin be excluded from the participation in, be denied the benefits of, or be otherwise subjected to discrimination under any Federal Aid Highway program or other activity for which the City of Renton receives Federal financial assistance.

Any person who believes they have been aggrieved by an unlawful discriminatory practice under Title VI has a right to file a formal complaint with the City of Renton. Any such complaint must be in writing and filed with the City of Renton Human Resources within one hundred, eighty (180) days following the date of the alleged discriminatory occurrence. Title VI Discrimination Complaint Forms may be obtained from the City's website (www.rentonwa.gov) or from the Human Resources office at no cost to the complainant by calling (425) 430-7655.

 

City of Renton | All Rights Reserved | Powered by CivicLive | © 2022 Intrado Corporation. | Disclaimer