Kennydale Reservoir and FS15

Contact Information

Fire Station 15 Ribbon Cutting

With the new Kennydale Fire Station 15 complete and in operation (February 1, 2019), construction has begun on the water reservoir, directly behind the station. The new reservoir is an above-ground design (100 feet above ground level with a diameter of about 50 feet). It will address long-identified needs for supply reliability, pressure surge control, and increased storage capacity within the Kennydale area for fire protection and domestic water use. Construction is expected to take about 12 months to complete.

Both activities are a collaboration of the Renton Regional Fire Authority and the city's facilities division and utility systems division.

Project Updates

July 2019

Construction has begun on the city's water reservoir directly behind the new Kennydale Fire Station 15 on N 30th St. You can expect the following construction activities:

  • Site grading work: Crews will begin using equipment to grade the site and prepare for retaining wall and foundation construction. This work will take approximately one

  • Auger cast pile and foundation installation: Equipment will be used to auger cast foundation piles for the reservoir. Auger cast piles are constructed with rebar baskets that are placed into the holes and then filled with concrete. Piles are then tied together with additional rebar prior to the mat foundation being poured. There will be no pile driving. This step is expected to take about three to four weeks.

  • Vertical construction: Once the foundation is complete, vertical construction of the steel reservoir tank will begin. Steel panels will be welded into place to form the reservoir.

  • Public art process: The reservoir will be painted with artwork after recommendations by the City of Renton's Municipal Arts Commission and approval by the city. An artist will be hired to help create mural concepts that reflect community ideas. Stay tuned to the project website and listserv for additional information about the public art process will be shared this summer.

  • Offsite water system improvements: Related offsite improvements to balance water system demands in the area are currently in design; work at several locations in the roadway is anticipated in the fall of 2019 until summer 2020. Additional information will be provided to neighbors as these improvements go into construction.

Reservoir construction is expected to take about 12 months to complete and will typically occur during the work week in normal daytime business hours (8 a.m. to 5 p.m.). No weekend work is expected.

Schedule

Construction of the fire station began in February 2018 and occupancy was achieved in February 2019.

Reservoir construction began in spring 2019 and take approximately 12 months.

Community Involvement

The city and RRFA worked closely with the community, providing updated information about the design and to solicit input at key points in the process.

The project team conducted outreach through community briefings and hosted a public meeting prior to submitting an environmental review and land use permit application.

Regular updates are sent via email and posted on this page.

Groundbreaking Video

Public Art Opportunity

The Renton Municipal Arts Commission will consider options and make recommendations for any painted treatment of the reservoir and invite public feedback through their process. A schedule for meetings related to reservoir public art will be announced on our website and through the project email list.

Click image to enlarge

Kennydale FS15 location map

Kennydale FS15 major water customers

Kennydale FS15 fire response zone

City of Renton | All Rights Reserved | Powered by CivicLive | © 2019 West Corporation. | Disclaimer