City of Renton Arterial Traffic Impacts

 

Week of February 20, 2017 

Note: All projects are weather permitting and unless otherwise noted streets will always remain open. Please note Harrington Avenue NE, Sunset Lane NE and Glennwood Avenue NE will be closed until approximately July 31, 2017  

South 2nd and Main Avenue South
Monday, February 20th through Sunday, February 26th. 
The two west lanes on Main between 2nd and 3rd will be closed for project improvements while the east lanes will be open for traffic flow. Approved traffic control plans have been issued for all work and will be followed. The on-site inspector is Pat Miller, 206-794-6162.

Monday, February 20th through Friday, February 24th, 8:30 am to 3:30 pm. Intermittent lane closures due to road construction for the 2nd and Main Capital Improvement Project. An approved traffic control plan has been issued and will be followed. Questions can be directed to Keith Wooley, 425-430-7318 or Mark Wetherbee, 206-999-1829.

Harrington Avenue NE and Glenwood Avenue NE 
Monday, February 20th through Friday, March 31st (2017). 
Full road closure on Harrington between Sunset Lane NE and Harrington Avenue NE as well as a full road closure on Harrington Avenue NE between NE 10th Street and Sunset Lane NE will be in place as part of the Sunset Lane Capital Improvement Project. Approved traffic control plans have been issued for all work and will be followed. Questions can be directed to Keith Wooley, 425-430-7318 or Mark Wetherbee, 206-999-1829.

S 14th Street
Monday, February 20th through Sunday, February 26th
. Road Closure on South 14th Street between Shattuck Avenue S through Smithers Avenue S for WSDOT Talbot Hill project. Open to local access only. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Patrick DeCaro, 425-207-6013.

116th Avenue SE
Monday, February 20th through Friday, February 24th, 8:30 am to 3:30 pm
. Intermittent lane closures with alternating traffic due to installation of sidewalk for the 116th Ave SE Sidewalk project. An approved traffic control plan has been issued and will be followed. Questions can be directed to Flora Lee at 425-430-7303 or Todd Freih at 206-999-1832.

Lake Washington Blvd N
Monday, February 20th through Friday, February 24th, 8:30 am to 3:30 pm.
 Intermittent Lake closures at Lake Washington Blvd just north of Houser Way N/Gene Coulon Park due to utility installation and possible road restoration. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Brad Stocco, 425-282-2373.

SW 7th Street
Monday, February 20th through Friday, February 24th, 7:00 am to 5:00 pm. 
Lane closures along SW 7th Street between Powell Avenue SW and Lind Avenue SW due to storm water Capital Improvement Project. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Dan Carey, 425-430-7293, or Pat Miller, 206-794-6162.