City of Renton Arterial Traffic Impacts

Week of January 22, 2018

Note:   All projects are weather permitting and unless otherwise noted streets will always remain open.  

Park Avenue North, Garden Avenue North, North 3rd Street, and North 4th Street
Tuesday, January 22nd through August 2018, 8:30 am to 4:45 pm.
Additional construction traffic due to the construction of Sartori Elementary School at the 300 block of Park Avenue North and Garden Avenue North. Questions may be directed to Patrick DeCaro, 425-207-6013.

S 14th Street
Monday, January 22nd through December 2018.
Road Closure on South 14th Street between Smithers Avenue S through Davis Avenue S for utility construction. Approved traffic control plans have been issued for all work and will be followed. Questions may be directed to Patrick DeCaro, 425-207-6013.

Talbot Road South
Monday, January 22nd through Friday, January 26th, 9:00 am to 3:00 pm.
Single lane closure along the northbound Talbot Road S between northbound I-405 on-ramp to the southbound I-405 off-ramp for I-405 Direct Connector Project. Questions may be directed to Rohini Nair, 206-999-1822.

East Valley Road
Monday, January 22nd through Friday, January 26th, 8:30 am to 3:00 pm.
Northbound East Valley Road between SW 19th Street and Maple Avenue SW will be closed for I-405 Direct Connector Project. Questions may be directed to Rohini Nair, 206-999-1822.


 